Project Update - March 2025
- Paving contractor onsite completing the construction of concrete footings for flip-up anchors, backstroke flag posts, pool hoist, and sub-surface drainage works.
- Perimeter pool paving to commence.
- Facility building footings and buildings arrive onsite, with building commissioning to commence in April.
- Pool lighting installation will commence in late March.
- Stage 1 of Garrison Fencing works to commence.
The Nullagine Pool is a priority project for the Shire of East Pilbara in 2024/25 and will provide an important aquatic recreation facility for the Nullagine community. This project is a partnership between the Shire of East Pilbara, the Australian Government and Atlas Iron.
Project includes:
- 4x lane 25m pool
- 6m x 6m Toddler pool
- Change rooms
- Kiosk and first aid
- Change rooms
- Shaded grassed areas
Your Say Questions
Have a question about the Nullagine Pool? Let the Project team know your question...
Page last updated: 07 Mar 2025, 10:58 AM
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends