Category #Nullagine   Show all

  • Nullagine Pool Update - March 2024

    Share Nullagine Pool Update - March 2024 on Facebook Share Nullagine Pool Update - March 2024 on Twitter Share Nullagine Pool Update - March 2024 on Linkedin Email Nullagine Pool Update - March 2024 link
    supporting image

    Completed Works:

    • Earth works and site preparation for the main pool and toddler pool
    • Pool brickwork, pool base concreting and pool perimeter pipe works

    What’s next:

    • Fabrication and installation of plant room building
    • Plant room fit out and commissioning
    • Fabrication and installation of change rooms and kiosk buildings
    • Pool liner installation

    The Nullagine Pool is a priority for the Shire of East Pilbara in 2023/24 and will provide an important aquatic recreation facility for the Nullagine community.