Nullagine Pool Update - March 2024
Completed Works:
- Earth works and site preparation for the main pool and toddler pool
- Pool brickwork, pool base concreting and pool perimeter pipe works
What’s next:
- Fabrication and installation of plant room building
- Plant room fit out and commissioning
- Fabrication and installation of change rooms and kiosk buildings
- Pool liner installation
The Nullagine Pool is a priority for the Shire of East Pilbara in 2023/24 and will provide an important aquatic recreation facility for the Nullagine community.